KEFI Gold and Copper Unveils Plans for Tulu Kapi Underground Mine

Instruments
Gold Copper
Share

KEFI Gold and Copper has announced updated plans for its Tulu Kapi Underground Mine in Ethiopia, which is expected to contribute significantly to the company's gold production. The new plan estimates that the mine will produce around ~250koz of gold per year, up from the previous estimate of ~200koz. This increase is due to a lower cut-off grade and higher gold price assumptions.

The underground mine is expected to be developed using open pit funds, with engineering studies set to be completed in 4Q27. The decline development will start after open pit commissioning in mid-2028, followed by infill and step-out drilling from underground and an updated mineral resource estimate in 2029.

The combined open pit and underground mine is estimated to produce around ~1.2moz of gold over a 7-8 year life of mine (LOM), with an all-in sustaining cost (AISC) of $1,100-1,300/oz. The post-tax net present value (NPV5) at a $2,350/oz gold price is estimated to be around ~$274m, with an internal rate of return (IRR) of 220% and a payback period of just 9 months.

More on Commodities

Disclaimer: Guavy is a data and market intelligence provider, not an investment adviser. The information, signals, and market analysis provided by the Guavy API and related services are for informational purposes only and are not intended as financial advice, investment recommendations, or an endorsement of any particular trading strategy. Trading in volatile markets, including cryptocurrency, carries significant risk and may not be suitable for all investors. Past performance is not indicative of future results. Users should consult with a qualified financial professional before making any investment decisions. Guavy makes no guarantee of trading profits or financial returns.

Market sentiment intelligence for apps, funds & agents

Location

729 55 Ave SW
Calgary AB T2V 0G4
Canada

© 2026 Guavy Inc