The Pakistani government has apologized for temporary night-time loadshedding due to the unavailability of regasified liquefied natural gas (RLNG).

Citing a 3,600MW shortfall resulting from delayed RLNG cargoes, the Power Division spokesperson said that temporary load management of 1.5 to three hours was carried out during last night's peak hours.

A 195MW decline in generation from Mangla Dam and the use of furnace oil-based power plants contributed to the shortage.

The Power Division assured consumers that load management will be reduced as soon as the delayed RLNG cargoes arrive, which will bring down the cost of RLNG-based power generation.

The government had previously apologized for loadshedding exceeding 2.25 hours in April due to lower water availability for power generation.

More on Commodities

Disclaimer: Guavy is a data and market intelligence provider, not an investment adviser. The information, signals, and market analysis provided by the Guavy API and related services are for informational purposes only and are not intended as financial advice, investment recommendations, or an endorsement of any particular trading strategy. Trading in volatile markets, including cryptocurrency, carries significant risk and may not be suitable for all investors. Past performance is not indicative of future results. Users should consult with a qualified financial professional before making any investment decisions. Guavy makes no guarantee of trading profits or financial returns.

Market sentiment intelligence for apps, funds & agents

Location

729 55 Ave SW
Calgary AB T2V 0G4
Canada

© 2026 Guavy Inc