CleanSpark Diversifies into Energy Infrastructure Compute
CleanSpark has outlined a strategic shift toward 'energy infrastructure compute' in its investor presentation. This move expands beyond pure-play Bitcoin mining, marking a significant change for the company.
The U.S. footprint slide shows contracted capacity of 885 MW, with additional contracted MW figures listed at 638, 399, 110, 63, and 15.
CleanSpark's development platform is positioned at more than 2 GW, with AI/HPC sites described as leased or under exclusivity. The company has also highlighted its Texas pipeline, noting that Sealy power is fully approved, while Brazoria power is planned in two 300 MW phases subject to ERCOT approval.
In Georgia, the company references Washington site, mentioning ongoing data center leasing discussions.