Bitdeer AI Deploys Nvidia Capacity in Malaysian Data Center
Bitdeer AI has deployed Nvidia GB300 NVL72-based capacity in a data center in Malaysia, part of its broader push into the AI cloud market. The A102 data center will offer 9.5MW once operational and 50 percent of its capacity has been contracted under a five-year long-term offtake commitment with a total value of $400 million.
The facility is purpose-built for rack-scale liquid-cooled AI deployments, and Bitdeer AI is in ongoing negotiations for the remaining capacity at the site. The company aims to contract and bring online 350MW of AI cloud capacity by the first quarter of 2028.
Bitdeer AI's parent company, Bitdeer Technologies Group, has 175,000 Bitcoin mining machines under management and operates six sites worldwide. In February 2025, Bitdeer acquired a 101MW gas-fired power project in Canada for $21.7 million, with plans to develop a 99MW Bitcoin mining site.