Uzbekistan's President Shavkat Mirziyoyev has criticized officials for selecting an incorrect site for the Surkhandarya power plant, which will cost an additional $300 million to supply natural gas.

The project, being built by SCE-Quvvat in Angor district, was initially announced with participation from Nebras Power of Qatar, Stone City Energy of the Netherlands, Siemens Energy and France's EDF.

Mirziyoyev stated that the site selection was made without considering the costs of connecting the plant to the gas supply network, resulting in substantial additional investment.

More on Commodities

Disclaimer: Guavy is a data and market intelligence provider, not an investment advisor. The information, signals, and market analysis provided by the Guavy API and related services are for informational purposes only and are not intended as financial advice, investment recommendations, or an endorsement of any particular trading strategy. Trading in volatile markets, including cryptocurrency, carries significant risk and may not be suitable for all investors. Past performance is not indicative of future results. Users should consult with a qualified financial professional before making any investment decisions. Guavy makes no guarantee of trading profits or financial returns.

Real-time market sentiment intelligence for apps, funds & agents

Location

729 55 Ave SW
Calgary AB T2V 0G4
Canada

© 2026 Guavy Inc