SNT Energy Completes $52.2M Equipment Supply for South Korea's First Coal-to-LNG Conversion Plant

Instruments
Natural Gas
Share

SNT Energy has completed the supply of core equipment worth ₩72.2 billion (approximately $52.2 million) to South Korea's first coal-to-LNG conversion plant, the Gumi Natural Gas Power Plant.

The company received an order from Korea Western Power in February 2023 for heat recovery steam generators (HRSGs) and related auxiliary equipment valued at ₩72.2 billion.

The HRSGs supplied by SNT Energy are central to the combined cycle efficiency of the plant, which is expected to reduce carbon dioxide emissions by nearly half compared to coal-fired generation.

An SNT Energy representative stated, 'With this HRSG supply, we have demonstrated our technical capabilities and comprehensive project execution competence in the HRSG sector linked to high-efficiency large gas turbines.'

More on Commodities

Disclaimer: Guavy is a data and market intelligence provider, not an investment adviser. The information, signals, and market analysis provided by the Guavy API and related services are for informational purposes only and are not intended as financial advice, investment recommendations, or an endorsement of any particular trading strategy. Trading in volatile markets, including cryptocurrency, carries significant risk and may not be suitable for all investors. Past performance is not indicative of future results. Users should consult with a qualified financial professional before making any investment decisions. Guavy makes no guarantee of trading profits or financial returns.

Market sentiment intelligence for apps, funds & agents

Location

729 55 Ave SW
Calgary AB T2V 0G4
Canada

© 2026 Guavy Inc