Oracle's Project Jupiter AI data center in New Mexico has hit a snag. The tech giant filed a force majeure declaration, which protects it from financial obligations if the facility fails to launch by its scheduled 2028 target.

The move sent Oracle's shares down approximately 4%, while Blue Owl Capital and Bloom Energy declined by 4% and 6%, respectively.

At issue is a critical natural gas pipeline required for the project, which has been postponed until February 2027. The delay is due to New Mexico State Land Office's continued rejection of right-of-way authorization across state trust territories, with community leaders and environmental advocacy organizations opposing the project.

The force majeure declaration was filed by Oracle to safeguard itself from potential penalties if the data center misses its deadline. The company asserts that 'Project Jupiter remains on our planned schedule,' but the legal filing indicates genuine concern about meeting the established timeline.

More on Crypto

Disclaimer: Guavy is a data and market intelligence provider, not an investment adviser. The information, signals, and market analysis provided by the Guavy API and related services are for informational purposes only and are not intended as financial advice, investment recommendations, or an endorsement of any particular trading strategy. Trading in volatile markets, including cryptocurrency, carries significant risk and may not be suitable for all investors. Past performance is not indicative of future results. Users should consult with a qualified financial professional before making any investment decisions. Guavy makes no guarantee of trading profits or financial returns.

Market sentiment intelligence for apps, funds & agents

Location

729 55 Ave SW
Calgary AB T2V 0G4
Canada

© 2026 Guavy Inc