Texas Sets Deadline for Data Centers and Crypto Miners to Prove Interconnection Projects

Share

Texas energy regulators have set a deadline for data center and crypto-mining projects to prove their interconnection projects are real, funded, and ready to build. The Public Utility Commission of Texas (PUCT) and the Electric Reliability Council of Texas (ERCOT) have given operators until December 10, 2026, to provide ownership records, site access permissions, purchase orders, and contracts.

The deadline comes after ERCOT tracked a large number of large-load interconnection requests in late 2025. The queue consisted of approximately 226 GW of large-load interconnection requests, with around 90% attributed to data centers. Crypto-mining operations account for a smaller slice of the pie, but still a notable portion.

The verification process aims to separate real projects from speculative or 'zombie' ones that could be tying up grid planning resources and distorting infrastructure investment decisions. Governor Greg Abbott directed a comprehensive audit of ERCOT's interconnection queue in August 2026, leading to the deadline being set.

More on Crypto

Disclaimer: Guavy is a data and market intelligence provider, not an investment adviser. The information, signals, and market analysis provided by the Guavy API and related services are for informational purposes only and are not intended as financial advice, investment recommendations, or an endorsement of any particular trading strategy. Trading in volatile markets, including cryptocurrency, carries significant risk and may not be suitable for all investors. Past performance is not indicative of future results. Users should consult with a qualified financial professional before making any investment decisions. Guavy makes no guarantee of trading profits or financial returns.

Market sentiment intelligence for apps, funds & agents

Location

729 55 Ave SW
Calgary AB T2V 0G4
Canada

© 2026 Guavy Inc