TSMC’s first European semiconductor factory in Dresden, Germany, is progressing as planned, with mass production expected to begin by the end of 2027. The project, managed through the joint venture European Semiconductor Manufacturing Company (ESMC), has completed its main structure and held a topping-out ceremony in September 2026. The next key milestones include the installation of production equipment in mid-2027 and the hiring of the first staff later that summer.
The Dresden fab is designed to produce 40,000 12-inch wafers per month, targeting automotive and industrial applications. The facility will use two manufacturing processes: 28/22nm CMOS and 16/12nm FinFET. TSMC holds a 70% stake in the project, while Bosch, Infineon, and NXP each own 10%. Once fully operational, the plant is expected to create around 2,000 direct jobs.
The total investment for the project is approximately €10 billion, with €5 billion coming from German federal subsidies under the EU Chips Act. Groundbreaking occurred in August 2024, marking TSMC’s first production facility in Europe. Workforce training is already underway at TSMC’s headquarters in Taiwan to prepare new hires for the Dresden site.