Fed Watchdog: No Crimes in $2.4B Building Renovation, Only Mismanagement

Instruments
USD
Share

The Federal Reserve's $2.4 billion building renovation project has been marred by mismanagement, but no criminal violations were found by the Fed's internal watchdog.

The Inspector General (IG) report revealed that the Board of Governors and staff failed to secure a comprehensive cost estimate at the beginning of the project, nor did they establish a maximum overall cost. This led to inflated prices after construction began in 2022.

The original estimated cost was $921 million in February 2020, but by December 2024, it had more than doubled to $2.018 billion. The project's completion date has been pushed back from mid-2024 to December 2027.

Former Fed Chairman Jerome Powell, who remains on the board until January 2028, was criticized for his management of the project by the Trump administration and Republican members of Congress. President Donald Trump even visited the construction site last July, where he made an estimate of the project's expected costs that was corrected by Powell.

More on Forex

Disclaimer: Guavy is a data and market intelligence provider, not an investment adviser. The information, signals, and market analysis provided by the Guavy API and related services are for informational purposes only and are not intended as financial advice, investment recommendations, or an endorsement of any particular trading strategy. Trading in volatile markets, including cryptocurrency, carries significant risk and may not be suitable for all investors. Past performance is not indicative of future results. Users should consult with a qualified financial professional before making any investment decisions. Guavy makes no guarantee of trading profits or financial returns.

Market sentiment intelligence for apps, funds & agents

Location

729 55 Ave SW
Calgary AB T2V 0G4
Canada

© 2026 Guavy Inc