Fed's Building Renovation Project Finds Mismanagement, Not Crime

Instruments
USD
Share

The Federal Reserve's internal watchdog has released a report stating that the central bank mismanaged its $2.4 billion building renovation project, but did not find any evidence of criminal wrongdoing.

The report by the Fed's inspector general found that the board deviated from cost-management provisions and failed to secure a comprehensive cost estimate at the beginning of the project.

The construction costs doubled from an original estimate of $921 million in February 2020 to $2.018 billion by December 2024, with the project expected to last until December 2027, long past its originally slated completion date of mid-2024.

The report also found that a design change by the Fed in 2023 from an open workspace to mostly closed office space caused significant delays and increased costs.

More on Forex

Disclaimer: Guavy is a data and market intelligence provider, not an investment adviser. The information, signals, and market analysis provided by the Guavy API and related services are for informational purposes only and are not intended as financial advice, investment recommendations, or an endorsement of any particular trading strategy. Trading in volatile markets, including cryptocurrency, carries significant risk and may not be suitable for all investors. Past performance is not indicative of future results. Users should consult with a qualified financial professional before making any investment decisions. Guavy makes no guarantee of trading profits or financial returns.

Market sentiment intelligence for apps, funds & agents

Location

729 55 Ave SW
Calgary AB T2V 0G4
Canada

© 2026 Guavy Inc